1X00185H01
初步评估和拟定提案
A、 1.1合同的初步评估和建立通常应包括以下内容:
a) 确定组织高管理层提出的组织需求、要求和目标;
b) 初步评估组织在以下方面确定的需求、要求和目标:
1) 相关客户要求,
2) 符合相关标准要求,
3) 符合相关法律法规要求,
4) 目前的管理和运营方法,以及
5) 确定组织当前状况与已确定目标之间的差异,以:
实现;
c) 记录实现质量管理体系符合以下要求所需的活动:
a)中所述和b)4)中确定的需求、要求和目标;
d) 编制并向top提交实现活动的提案,如c)所述
管理是合同的基础。
A、 1.2合同应以明确的语言包括以下条款:
a) 质量管理体系咨询活动的范围,
b) 质量管理体系实现活动的策划,
c) 顾问和组织的承诺、作用、责任和产出,
d) 组织内部资源的承诺,
e) 支持顾问活动所需的组织成本,
f) 监测方法
g) 如何管理合同变更,
h) 保密性,
i) 适用标准,
j) 里程碑/交付日期,
k) 付款条件,以及
l) 时间框架。
1X00185H01

1X00185H01
Initial evaluation and preparation of a proposal A.1.1 Initial evaluation and establishment of a contract should typically include the following: a) identification of the organization's needs, requirements and objectives as presented by its top management; b) initial evaluation of the organization's identified needs, requirements and objectives with respect to 1) relevant customer requirements, 2) conformity with relevant standard requirements, 3) compliance with relevant statutory and regulatory requirements, 4) present managerial and operational methods, and 5) establishing the difference between the organization's current situation and the identified objectives to be achieved; c) documentation of the activities needed to achieve conformity of the quality management system with the needs, requirements and objectives as stated in a) and established by b) 4); d) preparation and presentation of a proposal for the realization of the activities, as defined in c), to top management as the basis for the contract. A.1.2 Contracts should include, in clear language, clauses concerning a) the scope of the quality management system consulting activity, b) planning of quality management system realization activities, c) the consultant's and the organization's commitment, role, responsibilities and outputs, d) commitment of the organization's internal resources, e) the organization's costs needed to support the consultant's activities, f) methods for monitoring g) how changes to the contract will be managed, h) confidentiality, i) applicable standards, j) milestones /delivery dates, k) terms of payment, and l) the time frame.
Copyright ©2019-2022 瑞昌明盛自动化设备有限公司 版权所有 赣ICP备2021006016号